How to Set Up R99 Fuel Delivery Across Multiple Bay Area Jobsites

Writer: JKI Marketing manager
JKI Marketing manager
4 days ago
2 min read
Excavator loading dump trucks at a construction site served by Dogpatch Biofuels’ Bay Area R99 renewable diesel delivery.

To set up R99 renewable diesel delivery across multiple Bay Area jobsites, give each location its own fuel profile and coordinate them through one delivery calendar. An Oakland earthmoving crew may need direct-to-equipment fueling, while a San Jose site with a shared tank may suit scheduled bulk refills. Match the method to fuel use, equipment staging and truck access.

Know what each jobsite needs per shift

Give every jobsite a record with its delivery entrance, site lead, cost code, equipment IDs, fuel grades and estimated gallons per shift. Include excavators, loaders, trucks and temporary generators if they draw from the same supply. For an existing tank, record the available fill capacity and who monitors the gauge.

Use recent delivery and equipment-hour records for an active site. For a new site, estimate demand from the planned hours and workload, then revise it after the first few visits. Recheck the estimate when a second shift starts, a larger excavator arrives or a generator begins running through the night. Those changes can alter the delivery schedule before they show up in the monthly invoice.

Choose a fueling method for each location

  • Wet-hose fueling fills parked equipment, vehicles and generators directly. It works well when a crew can stage units together in an approved fueling area and the foreman wants gallons tracked by asset.

  • Bulk fuel delivery replenishes an approved on-site tank. It can suit larger sites where several crews draw fuel throughout the day and someone can monitor inventory between deliveries.

  • A portable fuel cube can give a temporary site its own supply where storage is allowed. Dogpatch Biofuels offers 250- and 500-gallon units. Confirm usable capacity, placement and refill access when you ask about fuel cube rentals.

You can use all three methods across a single portfolio. Put each location's method, delivery window and site contact on the same calendar so a change at one jobsite reaches both dispatch and the superintendent.

Set up billing before the first truck rolls

Agree on reporting by site, asset and cost code before the first delivery. If a loader moves from Oakland to San Jose midweek, log the transfer so its next fill is charged to the right job. Keep delivery tickets with project records and compare gallons against equipment hours before investigating a cost increase; a new shift or an incorrect site code can explain the difference.

Dogpatch Biofuels provides R99 renewable diesel delivery for construction equipment in San Francisco, Oakland, San Jose and the greater Bay Area. Send your site list, estimated gallons, fuel grades and preferred days to request a multi-site construction fueling quote.

Frequently Asked Questions

Can one fuel supplier serve both trucks and off-road equipment?

Yes, if the supplier can provide the grade required for each group. List highway trucks, covered off-road equipment and stationary generators separately on your request. California requires R99 or R100 renewable diesel for covered off-road vehicles, with limited exceptions. See the CARB renewable diesel fuel requirements.

Can we test the fueling plan at one jobsite first?

Yes. Run a pilot at one representative site. After the first delivery, check actual gallons against the estimate, confirm the truck could reach the fueling point, and make sure the ticket shows the right job code. Use those findings when you set up the other sites.

 
 